Here is the Carson City road construction and maintenance report for the week of Aug. 26 to Sept. 1. Due to continued construction of the Carson City Freeway project the following road closures are in effect:
Roland Street is expected to close for 1 to 2 weekdays between Bigelow Drive and Ponderosa Drive for repaving.
Bigelow Drive has been permanently closed between Bennett Avenue and Roland Street and there may be periods of temporary closures between Roland Street and Appion Way.
Ponderosa remains open to local traffic, but minor delays with flaggers could be expected over the next month as drainage work continues in the area.
The intersection of Dat-So-La-Lee Way and Snyder Avenue will be closed for reconstruction. Local residents are advised to access Dat-So-La-Lee Way from the south via Clear Creek Avenue.
Major drainage crossings of South Carson Street between the Spooner Interchange and Snyder Avenue are currently expected to occur over a series of weekends in September. During these weekends, traffic will be restricted to 2 lanes in each direction during daytime hours and down to 1 lane per direction at night. Tentatively this work is scheduled for the weekends of September 6-8, September 13-15, September 19-21.
The following streets will be impacted by utility work:
— Valley Street between Robinson Street and Fifth Street. The street will be open, but there will be traffic control.
— Work on Gordon Street between Fairview Drive and Brown Street will begin August 28. The work will be on weekdays for approximately two weeks. There will be traffic control with flaggers.
Due to a special event, West Third Street between Carson Street and Curry Street will be closed from 1:30 pm to 11:30 pm on Friday, August 30.