The following is the Carson City road construction and maintenance report for the week of March 18-24: Snyder Avenue is closed between E. Roland Street and Center Drive because of continued construction of the Carson City Freeway project.
This portion of Snyder Avenue will remain closed for approximately nine months to allow for the construction of a bridge. Center Drive and Silver Sage Drive are also closed south of Appion Way. Bennett Avenue is closed between Center Drive and Bigelow Drive.
Those streets will be closed permanently to through traffic. Detours will be marked. Residents should expect additional roads serving north-south traffic to be closed in coming weeks, including Frontage Road and Bigelow Drive.
Utility work in the City will have the following traffic impacts:
— On Wednesday, March 20, work will begin on Rabe Way near the intersection with Center Drive. All work is expected to occur off of the roadway.
— There will be daytime work in the parking lane of Jewell Avenue.